1.1-A Resolution #06-33, San Leandro Unified School District School Facility Improvement Bond November 7, 2006
Recommended motion
Adopt Resolution #06-33, San Leandro Unified School District Facility Improvement Bond November 7, 2006.
- Staff Recommendation
- Adopt Resolution #06-33, San Leandro Unified School District Facility Improvement Bond November 7, 2006.
-
2.1-C Acceptance of Personnel Report Passed
Recommended motion
Accept Personnel Report as submitted.
- Staff Recommendation
- Accept Personnel Report as submitted.
Outcome
Approved as part of consent items (7-0 vote per minutes)
-
2.2-C Renewal of Student Teaching Agreements Business, Operations, and Passed
Recommended motion
Approve the renewal of the Student Teaching Agreements between the District and Saint Mary’s College.
- Staff Recommendation
- Approve the renewal of the Student Teaching Agreements between the District and Saint Mary’s College.
Outcome
Approved as part of consent items (7-0 vote per minutes)
-
4.1-C Award of Contract for Window Replacement, Madison Elementary Repair Phase II Passed
Recommended motion
Approve contract award for Bid Package #06-08, Window Replacement at Madison Elementary Repair Phase II, to Coulter Construction.
- Staff Recommendation
- Approve contract award for Bid Package #06-08, Window Replacement at Madison Elementary Repair Phase II, to Coulter Construction.
Outcome
Approved as part of consent items (7-0 vote per minutes)
Contracts and agreements on this agenda 2
Extracted automatically from the agenda items and attachments; amounts appear only when printed in the documents.
| Item | Vendor / party | Description | Amount |
|---|---|---|---|
| 2.2-C | Saint Mary’s College | Approve the renewal of the Student Teaching Agreements between the District and Saint Mary’s College. | — |
| 4.1-C | — | Approve contract award for Bid Package #06-08, Window Replacement at Madison Elementary Repair Phase II, to Coulter Construction. | — |