banner

Special Board Meeting
San Leandro USD
May 28, 2014 6:30PM
San Leandro City Council Chambers
835 E. 14th Street
San Leandro, CA 94577

0. CALL TO ORDER/ROLL CALL- 6:00 P.M.
Minutes:

President James called the meeting to order at 6:00 p.m.  It was noted that all Board members were present with the exception of Trustees Katz-Lacabe and L?pez.  

1. PUBLIC TESTIMONY - CLOSED SESSION ITEMS
Minutes:

There was no public testimony on Closed Session items.

2. RECESS INTO CLOSED SESSION- 6:00 P.M.
Minutes:

The Board recessed into Closed Session at 6:01 p.m.

3. CLOSED SESSION ITEMS
3.1. Public Employee Discipline/Dismissal/Release/ Hiring, Government Code Section 54957 Confidential agenda item.
3.2. Conference with Labor Negotiator (Government Code section 54957.6) Employee organizations: SLTA, CSEA, T/T, Unrepresented Groups, Designated Representative: John ThompsonConfidential agenda item.
3.3. Public Employee Appointment - Title: -High School Assistant Principal - 2 positions -Government Code 54957Confidential agenda item.
4. RECONVENE TO OPEN SESSION - 6:30 P.M.
Minutes:

The Board reconvened into Open Session at 6:30 p.m.  It was noted that Trustee L?pez arrived at 6:01 p.m. and Trustee Katz-Lacabe arrived at 6:03 p.m.

4.1. Report on Closed Session ActionConfidential agenda item.
4.2. Pledge of Allegiance
Minutes:

President James led the Pledge of Allegiance to the Flag.

4.3. Approval of Agenda
Minutes:

President James noted the following amendments to the agenda:

  • Pull Action Item 11d - Lease-Leaseback Contract with Strawn Construction for Project #14-01 (McKinley, Monroe, Roosevelt and Washington Elementary School Modernization and Voluntary Seismic Upgrade Amendment and Bancroft Middle School Voluntary Seismic Upgrade) and Project #14-04 (Jefferson Elementary School Modernization at the Multi-Purpose Room)
  • Move the Student Board Member Certificate of Commendation presentation up before the "Legal Statement" as the Student Board member needed to leave, so that she could perform in the San Leandro High School Band Concert this evening.  

The Board then approved the agenda for the Special Board Meeting held on May 28, 2014, as amended.

Staff Recommendation

Approve the agenda for the Special Board Meeting held on May 28, 2014.

Actions:
Motion

Approve the agenda for the Special Board Meeting held on May 28, 2014.

- Motion made by Ron Carey and a seconded by Vince J. Rosato.
Vote:
Yes Lance James.
Yes Ron Carey.
Yes Diana Prola.
Yes Mike Katz-Lacabe.
Yes Corina N. Lopez.
Yes Vince J. Rosato.
5. PRESENTATIONS
5.1. Student Board Member Certificate of Commendation
Minutes:

The Board of Education and the Superintendent presented Ellie Erickson with a Certificate of Commendation for her outstanding service as a Student Board Member for the San Leandro Unified School District Board of Education for the 2013-2014 school year. Each of the members and the Superintendent personally thanked Ellie for her service and wished her the best as she continues her educational journey at Cal Poly, San Luis Obispo.

Quick Summary/Staff Recommendation

The Board of Education and the Superintendent will present Ellie Erickson with a Certificate of Commendation for her outstanding service as a Student Board Member for the San Leandro Unified School District Board of Education for the 2013-2014 school year.

6. LEGAL STATEMENT
6.1. Legal Statement
Quick Summary/Staff Recommendation

Members of the audience who wish to address the Board are asked to complete the yellow card available at the entrance and submit it to the Board's Administrative Assistant. Speakers who have completed the card will be called when the item is reached on the agenda or, for non-agenda items, during the Public Testimony. Cards are to be turned in before the item is reached on the agenda. Please note that the meeting is being recorded.

State law prohibits the Board of Education from taking any action on or discussing items that are not on the posted agenda except to A) briefly respond to statements made or questions posed by the public in attendance; B) ask questions for clarification; C) provide a reference to a staff member or other resource for factual information in response to the inquiry; or D) ask a staff member to report back on the matter at the next meeting and/or put it on a future agenda. (Government Code 54954.2(a)).

7. PUBLIC TESTIMONY ON NON-AGENDA ITEMS
Minutes:

There was no public testimony on Non-Agenda Items.

8. REPORTS
8.1. Student Board Member Report
Minutes:

There was no report as Student Board member Ellie Erickson left early to perform in the San Leandro High School Band Concert.

9. CONSENT ITEMS
9.1. Approval of Consent Items
Minutes:

Dr. Rosanna Mucetti, Assistant Superintendent, asked that the first contract with Jennifer Beck Consulting, listed on the Contracts for Amounts $5,000 or Less for Fiscal Year 2013-2014 spreadsheet, be pulled.

The Board then approved the Consent Items as amended. 

Actions:
Motion
- Motion made by Corina N. Lopez and a seconded by Vince J. Rosato.
Vote:
Yes Lance James.
Yes Ron Carey.
Yes Diana Prola.
Yes Mike Katz-Lacabe.
Yes Corina N. Lopez.
Yes Vince J. Rosato.
Quick Summary/Staff Recommendation
These items are considered routine and may be enacted by a single motion. At the request of any member of the Board, any item on the consent agenda shall be removed and given individual consideration for action as a regular agenda item.
9.2. Personnel Reports
Attachments:
Classified Personnel Report
Certificated Personnel Report
9.3. Contract for Professional Services with Indoor Environmental Services (IES) for Proposition 39 Energy Conservation and Energy Efficiency Services
Fiscal Impact
Financing to be structured so that costs are paid by the utility cost savings and/or Proposition 39 funding associated with the energy conservation program.
TO:
Board of Education
 
Staff Recommendation
Approve the contract for Professional Services with Indoor Environmental Services (IES), in the amount not to exceed $58,500, for Proposition 39 Energy Conservation and Energy Efficiency Services.
Board Committee
Facilities and Technology Committee: May 14, 2014
Background Information
San Leandro Unified School District issued a Request for Qualifications (RFQ) on March 20, 2014, seeking the submittal of qualifications (SOQs) from interested firms capable of designing and implementing energy conservation, energy efficiency, energy generation and other energy related capital improvement services. On April 18, 2014, the District received eight (8) SOQs and interviewed the top four (4) candidates on May 1, 2014. Staff recommends Indoor Environmental Services (IES) for Proposition 39 Energy Conservation and Energy Efficiency Services, with a contract for professional services in the amount of not to exceed $58,500.
FROM:
Mike McLaughlin, Ed.D., Superintendent
Attachments:
Contract for IES for Proposition 39
9.4. Contracts for Amounts $5,000 or Less for Fiscal Year 2013-2014
Fiscal Impact
None, but each contract will be funded based on its budget source requested.
TO:
Mike McLaughlin, Ed.D., Superintendent
 
Staff Recommendation

Approve contracts on the attached spreadsheet which are for amounts $5,000 or less for fiscal year 2013-2014.

Board Committee
Finance Committee on June 20, 2011
Background Information
Attached is the "summary spreadsheet for all contracts $5,000 or less for fiscal year". The spreadsheet will be provided to the Board at every board meeting if there are any contracts falling under this category. Detailed contract information will not be part of the Board packet but will be available for questions or inspection upon request. For accounting purposes, each contract still requires submission of a requisition for approval by site administrator. All contracts require two signatures - Initiating Administrator and the Chief Business Officer or a Cabinet member.
FROM:
Song Chin-Bendib, Associate Superintendent, Business & Operations
Attachments:
Contracts $5,000 or Less Worksheet
9.5. Resolution #14-29 to Declare Certain Equipment Surplus and/or Obsolete
TO:
Board of Education
 
Staff Recommendation
Adopt Resolution #14-29 to declare equipment surplus and/or obsolete due to the age and condition of the designated equipment.
Policy/Code
Board Policy 3270(a); Administrative Regulations #3270 (a) #6.
Background Information
When district-owned books, equipment and supplies become unusable, obsolete, or no longer needed, the Superintendent or designee shall identify these items to the Governing Board, together with their estimated value and a recommendation that they be sold or disposed of by one of the methods prescribed in law and administrative regulations. With Board approval, the Superintendent or designee shall arrange for the sale or disposal of these items. Please see attached.
FROM:
Mike McLaughlin, Ed.D., Superintendent
Attachments:
Resolution 14-29 - Obsolete Equipment
10. ACTION/DISCUSSION ITEMS
10.1. Lease-Leaseback Contract with BRCO Constructors Inc. for Project #14-05 for the San Leandro High School Open Space Project; Project #14-11 for the San Leandro High School Renovation of Tennis Courts; and Project #14-13 for the San Leandro High School Exterior Site Work
Fiscal Impact
The cost of services is included in funded from Measure B, the November 2006 School Facilities General Obligation Bond Election.
TO:
Board of Education
 
Minutes:

Bond Director John Dominguez provided information with regards to the upcoming summer projects.  Detailing the scope of work for each project, Mr. Dominguez said that the amount of the Lease-Leaseback Contract with BRCO Construction was $1,979,507.  Projects include:

  • Project #14-05, for the San Leandro Open Space Project
  • Project #14-11 for the San Leandro High School Renovation of Tennis Courts
  • Project #14-13 for the San Leandro High School Exterior Site work

Harris & Associates Program Manager, Sefain Fernandez noted that in addition to the original scope of work at the high school, bleachers would be added to the softball and baseball fields, football stadium, and nets would be added to the varsity softball field.

It was reported that the projects will begin tomorrow, May 29, with a completion date will be August 15, 2014, with the exception of the bleachers, which may extend the completion time of the entire project to the end of October 2014. It was also noted that the scope of work does not include a scoreboard at the high school.

The Board then approved the Lease-Leaseback Contact with BRCO Constructors Inc. for Project #14-05 for the San Leandro High School Open Space Project; Project 
#14-11 for the San Leandro High School Renovation of Tennis Courts; an Project #14-13 for the San Leandro High School Exterior Site work.

Staff Recommendation

Approve the contract with BRCO Constructors, Inc., (the amount of this contract will be provided on 05/28/2014):

  • Project #14-05, for the San Leandro High School Open Space Project;
  • Project #14-11 for the San Leandro High School Renovation of Tennis Courts; and
  • Project #14-13 for the San Leandro High School Exterior Site Work.

 

Actions:
Motion

Approve the contract with BRCO Constructors, Inc., (the amount of this contract will be provided on 05/28/2014):

  • Project #14-05, for the San Leandro High School Open Space Project;
  • Project #14-11 for the San Leandro High School Renovation of Tennis Courts; and
  • Project #14-13 for the San Leandro High School Exterior Site Work.

 

- Motion made by Diana Prola and a seconded by Corina N. Lopez.
Vote:
Yes Lance James.
Yes Ron Carey.
Yes Diana Prola.
Yes Mike Katz-Lacabe.
Yes Corina N. Lopez.
Yes Vince J. Rosato.
Board Committee
Facilities and Technology Committee: May 14, 2014
Background Information

On February 4, 2014, the Board of Education received a presentation from Philip J. Henderson, Attorney at Law, Orbach Huff Suarez & Henderson LLP, on the Lease-Leaseback (LLB) Construction Project Delivery Method Available per Education Code Section 17406, which the District will use to deliver some of the bond construction projects in 2014. The basic structure of the LLB is as follows:

  • District leases real property to a builder for $1 (site lease)
  • Builder constructs facility, then leases the facility back to the district?this is the ?leaseback? component (facility lease)
  • District makes payments for construction costs:
  • Tenant improvement payments during construction
  • Lease payments after construction
  • The construction terms and conditions are part of an exhibit to the facility lease
  • Title to the new facility vests in the District as lease payments are made
  • District makes lease payments for a period of time and has the option to make a balloon payment to the builder to buy out the facilities lease

One of the benefits of using a LLB delivery method is that a district can utilize a best value evaluation to choose its builder.  Many districts have found that there are fewer performance issues using this method.  Although there is no guarantee of no change orders, many districts have also found fewer change orders under this method.

LLB contracts are still school district public work contracts and the builder must pay prevailing wages, issue bonds.  In addition, the District must still have DSA approval and Field Act compliance.  The District?s Project Stabilization Agreement may also be incorporated into each Lease Agreement.

Staff issued four RFQ?s to the general contracting public through advertisements in the Daily Review on March 18 and March 25, 2014.  The RFQs were also sent to thirteen (13) contractors who had previously worked successfully with the District and the design teams.  Nine general contractors responded to the RFQs on April 2.  Also, all nine (9) of the respondents met the District?s prequalification criteria.  On April 8 staff issued three (3) RFPs to the six (6) most qualified contractors and led mandatory site walks for each project.  Three (3) contractors responded to the RFPs and submitted proposals on the due date of April 25.

FROM:
Mike McLaughlin, Ed.D., Superintendent
Attachments:
Lease Leaseback Contract with BRCO Constructors Inc.
10.2. Agreement for Preliminary Services (Preconstruction Services) with Jeff Luchetti Construction Inc. for Project #14-07 for the Wilson Elementary School Parking Lot, Irrigation and Fields Project; Project #14-08 for the Madison Elementary School/District Office Parking Lot; and Project #14-12 for the Muir Middle School Parking Lot and Courtyard Landscaping
Fiscal Impact
The cost of services is included in funded from Measure B, the November 2006 School Facilities General Obligation Bond Election.
TO:
Board of Education
 
Minutes:

Harris & Associates Program Manager Serfain Fernandez explained that this Lease Leaseback Contract with Jeff Luchetti Construction Inc. is for preliminary/pre-construction services. The pre-construction services scope of work allows the contractor to work with the design team to look at ways to minimize costs. This is a three-month contract, not to exceed $26,100. Once the designs have been completed and construction costs identified, amendments to this contract will be brought back to the Board. Projects include:

  • Project #14-07 - Wilson Elementary School Parking Lot, Irrigation and Fields
  • Project #14-08 - Madison Elementary School/District Office Parking Lot
  • Project #14-12 - Muir Middle School Parking Lot and Courtyard Landscaping

The Board then approved the Agreement for Preliminary Services (Preconstruction Services) with Jeff Luchetti Construction Inc. for Project #14-07 for the Wilson Elementary School Parking Lot, Irrigation and  Fields Project;  #14-08 for the Madison Elementary School/District Office Parking Lot; and Project #14-12 for the Muir Middle School Parking Lot and Courtyard Landscaping. 

Staff Recommendation
Approve the Agreement for Preliminary Services (Preconstruction Services) with Jeff Luchetti Construction Inc. for Project #14-07 for the Wilson Elementary School Parking Lot, Irrigation and Fields Project; Project #14-08 for the Madison Elementary School/District Office Parking Lot; and Project #14-12 for the Muir Middle School Parking Lot and Courtyard Landscaping.
Actions:
Motion
Approve the Agreement for Preliminary Services (Preconstruction Services) with Jeff Luchetti Construction Inc. for Project #14-07 for the Wilson Elementary School Parking Lot, Irrigation and Fields Project; Project #14-08 for the Madison Elementary School/District Office Parking Lot; and Project #14-12 for the Muir Middle School Parking Lot and Courtyard Landscaping. - Motion made by Mike Katz-Lacabe and a seconded by Ron Carey.
Vote:
Yes Lance James.
Yes Ron Carey.
Yes Diana Prola.
Yes Mike Katz-Lacabe.
Yes Corina N. Lopez.
Yes Vince J. Rosato.
Board Committee
Facilities and Technology Committee: May 14, 2014
Background Information

On February 4, 2014, the Board of Education received a presentation from Philip J. Henderson, Attorney at Law, Orbach Huff Suarez & Henderson LLP, on the Lease-Leaseback (LLB) Construction Project Delivery Method Available per Education Code Section 17406, which the District will use to deliver some of the bond construction projects in 2014. The basic structure of the LLB is as follows:

  • District leases real property to a builder for $1 (site lease)
  • Builder constructs facility, then leases the facility back to the district?this is the ?leaseback? component (facility lease)
  • District makes payments for construction costs:
  • Tenant improvement payments during construction
  • Lease payments after construction
  • The construction terms and conditions are part of an exhibit to the facility lease
  • Title to the new facility vests in the District as lease payments are made
  • District makes lease payments for a period of time and has the option to make a balloon payment to the builder to buy out the facilities lease

One of the benefits of using a LLB delivery method is that a district can utilize a best value evaluation to choose its builder.  Many districts have found that there are fewer performance issues using this method.  Although there is no guarantee of no change orders, many districts have also found fewer change orders under this method.

LLB contracts are still school district public work contracts and the builder must pay prevailing wages, issue bonds.  In addition, the District must still have DSA approval and Field Act compliance.  The District?s Project Stabilization Agreement may also be incorporated into each Lease Agreement.

Staff issued four RFQ?s to the general contracting public through advertisements in the Daily Review on March 18 and March 25, 2014.  The RFQs were also sent to thirteen (13) contractors who had previously worked successfully with the District and the design teams.  Nine general contractors responded to the RFQs on April 2.  Also, all nine (9) of the respondents met the District?s prequalification criteria.  On April 8 staff issued three (3) RFPs to the six (6) most qualified contractors and led mandatory site walks for each project.  Three (3) contractors responded to the RFPs and submitted proposals on the due date of April 25.

Staff recommends awarding the Agreement for Preliminary Services (Preconstruction Services) to Jeff Luchetti Construction pending DSA approval of the projects.  Following DSA approval, the District and Contractor intend to enter into contract to construct the projects under a LLB contract.

FROM:
Mike McLaughlin, Ed.D., Superintendent
Attachments:
Agreement with Jeff Luchetti Construction Inc.
10.3. Lease-Leaseback Contract with Rodan Builders for Project #14-03 for the Madison Elementary School Classroom Restroom Addition and Exterior Access
Fiscal Impact
The cost of services is included in funded from Measure B, the November 2006 School Facilities General Obligation Bond Election.
TO:
Board of Education
 
Minutes:

Harris Program Manager Serfain Fernandez explained that the scope of work includes three (3) additional restrooms at Madison Elementary School: One (1) new boys' standard restroom; One (1) new girls' standard restroom; and One (1) new Special Education restroom.  The cost for the three restrooms will be $208,144.65.  The work will begin on June 16 and will be completed by August 15, 2014.

Responding to Trustee Katz-Lacabe regarding of the possibility that the projects may not be completed before schools open on August 20, Mr. Fernandez said the project is expected to be completed two weeks earlier than August 15. 

The Board then approved the Lease-Leaseback Contract with Rodan Builders for Project #14-03 for the Madison Elementary School Classroom Restroom Addition and Exterior Access. 

Staff Recommendation
Approve the contract with Rodan Builders for Project #14-03 for the Madison Elementary School Classroom Restroom Addition and Exterior Access
Actions:
Motion
Approve the contract with Rodan Builders for Project #14-03 for the Madison Elementary School Classroom Restroom Addition and Exterior Access - Motion made by Mike Katz-Lacabe and a seconded by Ron Carey.
Vote:
Yes Lance James.
Yes Ron Carey.
Yes Diana Prola.
Yes Mike Katz-Lacabe.
Yes Corina N. Lopez.
Yes Vince J. Rosato.
Board Committee
Facilities and Technology Committee: May 14, 2014
Background Information

On February 4, 2014, the Board of Education received a presentation from Philip J. Henderson, Attorney at Law, Orbach Huff Suarez & Henderson LLP, on the Lease-Leaseback (LLB) Construction Project Delivery Method Available per Education Code Section 17406, which the District will use to deliver some of the bond construction projects in 2014. The basic structure of the LLB is as follows:

  • District leases real property to a builder for $1 (site lease)
  • Builder constructs facility, then leases the facility back to the district?this is the ?leaseback? component (facility lease)
  • District makes payments for construction costs:
  • Tenant improvement payments during construction
  • Lease payments after construction
  • The construction terms and conditions are part of an exhibit to the facility lease
  • Title to the new facility vests in the District as lease payments are made
  • District makes lease payments for a period of time and has the option to make a balloon payment to the builder to buy out the facilities lease

One of the benefits of using a LLB delivery method is that a district can utilize a best value evaluation to choose its builder.  Many districts have found that there are fewer performance issues using this method.  Although there is no guarantee of no change orders, many districts have also found fewer change orders under this method.

LLB contracts are still school district public work contracts and the builder must pay prevailing wages, issue bonds.  In addition, the District must still have DSA approval and Field Act compliance.  The District?s Project Stabilization Agreement may also be incorporated into each Lease Agreement.

Staff issued four RFQ?s to the general contracting public through advertisements in the Daily Review on March 18 and March 25, 2014.  The RFQs were also sent to thirteen (13) contractors who had previously worked successfully with the District and the design teams.  Nine general contractors responded to the RFQs on April 2.  Also, all nine (9) of the respondents met the District?s prequalification criteria.  On April 8 staff issued three (3) RFPs to the six (6) most qualified contractors and led mandatory site walks for each project.  Three (3) contractors responded to the RFPs and submitted proposals on the due date of April 25.

FROM:
Mike McLaughlin, Ed.D., Superintendent
Attachments:
Lease Leaseback Contract - Rodan
10.4. Lease-Leaseback Contract with Strawn Construction for Project #14-01 (McKinley, Monroe, Roosevelt and Washington Elementary School Modernization and Voluntary Seismic Upgrade Amendment and Bancroft Middle School Voluntary Seismic Upgrade) and Project #14-04 (Jefferson Elementary School Modernization at the Multi-Purpose Room)
Fiscal Impact
The cost of services is included in funded from Measure B, the November 2006 School Facilities General Obligation Bond Election.
TO:
Board of Education
 
Minutes:

This item was pulled from the agenda.

Staff Recommendation

Approve the contract with Strawn Construction (the amount of this contract will be provided on 5/28/14) for

  • Project #14-01, for McKinley, Monroe, Roosevelt and Washington Elementary School Modernization and Voluntary Seismic Upgrade and Bancroft Middle School Voluntary Seismic Upgrade; and
  • Project #14-04 for the Jefferson Elementary School Modernization at the Multi-Purpose Room.

 

Board Committee
Facilities and Technology Committee: May 14, 2014
Background Information

On February 4, 2014, the Board of Education received a presentation from Philip J. Henderson, Attorney at Law, Orbach Huff Suarez & Henderson LLP, on the Lease-Leaseback (LLB) Construction Project Delivery Method Available per Education Code Section 17406, which the District will use to deliver some of the bond construction projects in 2014. The basic structure of the LLB is as follows:

  • District leases real property to a builder for $1 (site lease)
  • Builder constructs facility, then leases the facility back to the district?this is the ?leaseback? component (facility lease)
  • District makes payments for construction costs:
  • Tenant improvement payments during construction
  • Lease payments after construction
  • The construction terms and conditions are part of an exhibit to the facility lease
  • Title to the new facility vests in the District as lease payments are made
  • District makes lease payments for a period of time and has the option to make a balloon payment to the builder to buy out the facilities lease

One of the benefits of using a LLB delivery method is that a district can utilize a best value evaluation to choose its builder.  Many districts have found that there are fewer performance issues using this method.  Although there is no guarantee of no change orders, many districts have also found fewer change orders under this method.

LLB contracts are still school district public work contracts and the builder must pay prevailing wages, issue bonds.  In addition, the District must still have DSA approval and Field Act compliance.  The District?s Project Stabilization Agreement may also be incorporated into each Lease Agreement.

Staff issued four RFQ?s to the general contracting public through advertisements in the Daily Review on March 18 and March 25, 2014.  The RFQs were also sent to thirteen (13) contractors who had previously worked successfully with the District and the design teams.  Nine general contractors responded to the RFQs on April 2.  Also, all nine (9) of the respondents met the District?s prequalification criteria.  On April 8 staff issued three (3) RFPs to the six (6) most qualified contractors and led mandatory site walks for each project.  Three (3) contractors responded to the RFPs and submitted proposals on the due date of April 25.

FROM:
Mike McLaughlin, Ed.D., Superintendent
Attachments:
Lease Leaseback Contract - Strawn Construction
11. ADDITIONAL SUGGESTIONS AND COMMENTS FROM BOARD MEMBERS
Minutes:

Trustee Carey reminded that Board that the San Leandro High School Advanced Placement (AP) and Studio Art Exhibition will be tomorrow night, May 29, 4-7 p.m. at the San Leandro High School Arts Education Center (AEC) Gallery.

Trustee Prola commented that Bancroft Middle School will also be hosting their Civilizations of the World Faire tomorrow night, May 29, from 6:00-7:45 p.m. The Cherry Festival is this weekend, and she reminded the Board to sign up to "man the booth."  

Trustee Rosato reported that he attended the San Leandro High School Jazz Spring Concert, May 27 at the Arts Education Center.  He will be traveling to Los Angeles for the CTA State Council of Education conference this weekend.

Trustee Katz-Lacabe attended the Bancroft Musical Theatre Annual spring musical: Hairspray commenting that it was a nice production and well done. In response to Trustee Katz-Lacabe regarding the process for replacing Trustee Toro who resigned, Superintendent McLaughlin said that he spoke with legal counsel and confirmed that the election code says: "If a vacancy occurs from six months to 130 days before a regularly scheduled Board election at which the position is not scheduled to be filled, a special election to fill the position shall be consolidated with the regular election," adding that the person so elected shall serve only until the end of the term of the position which he/she was elected to fill. 

Trustee L?pez attended the candlelight vigil held for San Leandro High School student Brittney Silva, along with Trustees Katz-Lacabe and Assistant Superintendent John Thompson, noting that it was wonderful see all the support for the family.

Trustee James commented that because of the number of participants in the Cherry Festival Parade, it has been suggested that participants be dropped off at the corner of Marina Blvd. and Washington Avenue and walk up to the Boys and Girls Club. He also reminded the Board to sign up to volunteer to "man the booth."  He also announced that Monday, June 2, is the Adult School Graduation, 7 p.m. at the Arts Education Center. 

12. ANNOUNCEMENT
12.1. Board of Education Meetings
Minutes:
  • Regular Board Meeting - June 3, 2014 Cancelled
  • Regular Board Meeting - June 17, 2014
  • Special Board Meeting - June 24, 2014 - City Council Chambers

 

Quick Summary/Staff Recommendation
  • Regular Board Meeting - June 3, 2014 Cancelled
  • Regular Board Meeting - June 17, 2014
  • Special Board Meeting - June 24, 2014 - City Council Chambers
13. ADJOURNMENT*
13.1. Time
Minutes:

The meeting was adjourned at 6:55 p.m.

Actions:
Motion
- Motion made by Vince J. Rosato and a seconded by Mike Katz-Lacabe.
Vote:
Yes Lance James.
Yes Ron Carey.
Yes Diana Prola.
Yes Mike Katz-Lacabe.
Yes Corina N. Lopez.
Yes Vince J. Rosato.
Disability Information:
In compliance with the Americans with Disabilities Act, if you need special assistance to access the meeting room or to otherwise participate at this meeting, including auxiliary aids or services, please contact the Superintendent’s Office at (559) 646-2731. Please contact the District 24-hours in advance so that the District may make reasonable arrangements to ensure accessibility to the Board meeting. The District welcomes Spanish and other language speakers to Board meetings. Anyone planning to attend and needing an interpreter should call (559) 646-2731. Please contact the District 24-hours in advance so that arrangements can be made for an interpreter. El Distrito da la bienvenida a las personas que hablan español y otros idiomas a las juntas de la Mesa Directiva. Si Usted planea asistir y necesita interpretación, favor de llamar al (559) 646-2731. Favor de llamarnos al menos de 24-horas antes de la junta, para poder hacer arreglos de interpretación.
( Original )
PresentLinda Pollard
PresentJohn Thompson, Ed.D.
PresentLance James
PresentRon Carey
PresentDiana Prola
PresentMike Katz-Lacabe
PresentSong Chin-Bendib
PresentCorina N. Lopez
PresentVince J. Rosato
PresentMichael McLaughlin, Ed.D.
PresentRosanna Mucetti, Ed.D.
PresentEllie Erickson

The resubmit was successful.